Client:

Parrish Medical Center 

Titusville, Florida

Mr. Chris Male (Senior V. P.)

 

Honeycutt & Associates, Inc.

Design Team:

Rodney M. Honeycutt, P.E. (Principal)

G. W. McCulloch, P.E (Proj Manager)

David J. Pugh (Design Engineer)

Woody Rice, P.E (Engineer/Environ)

D. W. Wright, P.L.S. (Project Surveyor)

 

Description:

The project covers 50 acres and includes 210 patient care units, stormwater management facilities with regional design considerations for interfacing and connections to the proposed Chain of Lakes project.  FDOT access and road realignments were implemented for safety and vehicle access issues.  The area included designing 2.56 acres of created wetlands adjacent to the Indian River Lagoon Blue-way for mitigating wetland impacts.

 

Construction Cost:

70 million dollars

 

Current Phase:

The project consist of several phases:

Phase 1:Site Development/ Steel

Phase 2:Construction Medical Facility

Phase 3:N. & S. Building Restoration

Phase 4:Ex. Hospital Decommissioning

 

Completion Date:

This 70 million dollar project was completed in late 2002

 

Other Projects:

PMC Health & Fitness Center

PMC Port St. John Medical Offices

PMC Children’s Services Center

​​​​​​​Parrish Medical Center
pic of Parrish Medical Center/Hospital in Titusville

This 70 million dollar project includes a 6 story 210 bed medical facility covering over 52 acres, six individual out parcels, wetland creation along the Indian River Lagoon blue-way, stormwater master planning with regional wide impacts including the proposed Chain of Lakes project, coordination efforts with all permitting agencies (FDEP, USCOE,


​​​​​​​
PMC aerial pic

SJRWMD, FAA, FDOT, City of Titusville, and Brevard County), adjacent land owners negotiations, zoning, annexation, scheduling, and budgetary elements. PMC has looked to Honeycutt & Associates for their civil engineering and surveying expertise for project design and permitting.  HAI’s local knowledge of the site, local utilities codes, geographical parameters and surrounding development coupled with their dedication to quality has assured the client another great project.  The PMC project phase 1 is complete and included site development, structural steel erection, and the Central Energy Plant Construction.  Phase II of the development is nearing completion and include the actual 210 bed medical facility construction.

Pic of PMC Children's Center sign & building

HAI has worked with PMC on several area projects including:  North Brevard Children’s Services Center which had a budget of  $1.8 million with a 15,000 S.F. facility on 5.25 acres.  This facility has a children’s learning center, medical office space and has a therapeutic children’s playground.  The project came in on budget and was completed early; due to the dedication and commitment from PMC, design and construction representatives  This facility opened their doors in August 2000.

PMC PSJ US1 building

The Parrish Medical Center’s Port St. John medical office is a 22,000 S.F. facility covering 5 acres.  All phases have been completed on time and within budget. This facility is now operational bringing quality health care to the Port St. John Area.

PMC Fitness Center SR50 Titusville

The PMC Health & Fitness Center located on Hwy 50 in Titusville includes ½ mile of jogging trails, an indoor swimming pool, weight rooms, aerobic center, offices and locker rooms. This facility incorporated the natural beauty of the area giving this facility a relaxing and a quiet setting for continued preventive care. 

​​​​​​​Honeycutt and Associates has completed several projects with clients such as Parrish Medical Center due to providing dedication, long term commitment to quality and meeting the clients needs.